Case study

Fast Track Modular Suite

Grade D Modular Oncology Cleanroom Suite

The details

Our role:

Design & Build Principal Contractor

Scope:

Full Turnkey Design, Supply and Installation

Facility type:

Grade D MHRA licenced facility

Floor area:

320 m2

Contract value:

£2m

Programme:

3 months

Enbloc were chosen by the University Hospital Southampton NHS Foundation trust to provide a modular GMP oncology suite as Design and Build contractor.

The project was critical to the hospitals needs and urgently required therefore we conducted the project fast track with partial build off-site to accelerate the programme to only 3 months.

The facility was lifted into position onto pre-prepared foundations.

Within the facility there are Grade D cleanrooms to house Amercare Isolators, support areas including a Changing rooms,  Preparation rooms, Check / Release areas.

The facility has received MHRA approval and is manufacturing treatments for the Oncology department of the hospital.

The suite provides a modern environment that optimises workflow for materials, product, personnel, and waste.