+44 01252 626229 Email Linked In

Case study

Modular Cleanroom

Off site manufacturer modular bulk fill facility for Avecia

  • Building in situ with link corridor

  • New modular building being craned

  • Portable cleanroom trucked to site

The details

Our role:

Design and Build as Principal Contractor

Scope:

M&E + Construction

Facility type:

Grade C Modular Bulk Fill Facility

Floor area:

60 m2

Contract value:

£250k

Programme:

8 months

Through negotiation on Enbloc’s Partnership scheme, the contract for Avecia’s new modular bulk fill facility was a welcome challenge for Enbloc. Avecia required an extension to their ABC2000 plant to match visually both internally and externally. The brief included a preference for the extension to be modular and, therefore, built and fitted-out off site; Enbloc designed a painted steel module to match the existing grey facades.

The unit was fitted-out off-site (up to 70% complete) meaning on-site works were quickly finished once hook-ups were completed. The unit houses a Grade C bulk fill room and Grade D materials air locks with rapid roller doors and personnel changes both in and out of the main room, along with a plant area at one end.

Download this case study »